contact@octistech.com

Skip Navigation Links
 
 
 
   
 
 
 
Projects
 

Some projects or assignments in the area of fire and explosion investigation, forensic investigation, design review and maintenance engineering, which we have completed, are listed below.

• Fire and explosion involving incendiary fire, chemical fire,
   fire of electrical origin, etc. (investigation or expert witness):
  - Power plants
  - Coal handling facilities
  - Boilers
  - Substations
  - Warehouses
  - Marine vessels
  - Oil rig
  - Apartments
  - Buildings
  - Data centres
  - UPS rooms

• Failure or fire investigation of power generation equipment such as:
  - 137.5-MVA 11.5 kV steam turbine generator
  - 30-MVA 11 kV gas turbine generator
  - 21-MVA 15 kV diesel engine generator
  - 48-MVA 11.5 kV gas turbine generator
  - 50-MVA 11 kV gas turbine generator
  - 30-MVA 11 kV gas turbine generator
  - 100-MW coal-fired generator

• Failure or fire investigation of power transformers such as:
  - 500-MVA 500/150/66 kV interbus transformers
  - 470-MVA 500/23 kV generator step-up transformer
  - 550-kV outdoor bushings of 300 MVA 525/15.75 kV transformer
  - 292-MVA 150/15-kV generator step-up transformers
  - 150-MVA 230/66 kV transformers
  - 140-MVA generator step-up transformer
  - 310-MVA 19/275 kV generator step-up transformer
  - 67.5-MVA 13.8/115/6.3 kV generator step-up transformer
  - 80-MVA 132/33/11 kV transformer
  - 50-MVAr shunt reactor
  - 10-MVA rectifier transformer
  - 1-MVA 25-kV traction transformer

• Failure or fire investigation of switchgears and test equipment such as:
 - 230-kV Gas Insulated Switchgears (GIS) (e.g., 230-kV busbars,
    single-break and double break circuit breakers, disconnecting switch,
    voltage transformer)
 - 230-kV shunt reactors and test equipment.

 

• Failure or fire investigation of machinery and power distribution equipment
   such as:
  - 66-kV switchgears
  - 22-kV switchgears
  - 22/0.4 kV transformers
  - low-voltage switchboards and circuit breakers
  - cables and accessories (e.g., terminations for stress grading)
  - a.c. and d.c. motors and controllers
  - bus-ducts
  - distribution boards and automatic transfer switch
  - wirings
  - uninterruptible power supply system
  - battery and charger system.

• Investigation into the cause of tripping of power system, process plants,
   chillers as well as power interruption which resulted in loss of production.

• Investigation into the cause of industrial and electrical accidents which
   resulted in physical injury and/or death.

• Design review of HV and LV power distribution network, starter circuits,
   etc.

• Investigation into the cause of failure of printed wire assemblies.

• Failure investigation of facade light fittings.

• Failure investigation of pumps of refrigerant systems.

• Writing of technical specifications for maintenance tests of electrical
   equipment.

• Risk assessment of an extra-high voltage electrical switching station.

• Fire risk assessment of a hotel.

• Expert witness for fire, fault, failure, accident and forensic engineering
   work including litigation support.

 



 
 
  Copyright © 2024 . Octis Technology Pte Ltd. | All Rights Reserved.